Case Study: Reconstruction and modernization of the mechanical treatment system at the wastewater treatment plant (Ostrów-Mazowiecka, Poland)

PROJECT: Reconstruction and modernization of the mechanical treatment system at the wastewater treatment plant located on Olszynowa Str. 16 in Ostrów Mazowiecka
CUSTOMER: Public utility company in Ostrów Mazowiecka Sp. z o.o.
SITE: Wastewater treatment facilities on Olszynowa Str. 16
COMMISSIONING: February – March 2021

Project Objectives

The objective of the project was to update and reconstruct the system of removing and collecting waste extracted from wastewater at the wastewater treatment plant in Ostrów Mazowiecka.

According to the modernization plan, the following equipment was delivered, installed and commissioned in February 2021:

  • Esmil RSK0815 step screen with 3 mm gaps
  • SGSM 0.9×2.6 (1.2) penstocks – 2 pcs.
  • Screenings compactor

Until recently, the wastewater treatment plant had been experiencing difficulties with overflowing the channel with wastewater, so it was decided to widen the channel and install a wider screen with a higher capacity.

Project Implementation

The equipment for the project was manufactured at the Esmil plant. The existing inlet channel was enlarged to properly position the screen according to the project requirements. After the completion of the construction work, the Esmil professionals proceeded to the installation and commissioning of the unit. The screen was commissioned in March 2021.

Results

Thanks to the use of the Esmil RSK0815 step screen, the problem of overflowing the channel with wastewater was completely eliminated. The screen selected and supplied by Esmil not only keeps the mechanical treatment facility clean, but also, thanks to its reliable operation, protects the equipment on the further stages of the wastewater treatment process.

Reference on the operation of APKV-120 aerators (Budapest, Hungary)

The Southern Wastewater Treatment Plant in Budapest, with a capacity of 80,000 m3 per day, operates on the basis of the technology of biological wastewater treatment using activated sludge and aeration system regulated by the content of dissolved oxygen in 8 cascade aeration tanks.

Until the end of 2018, we used exclusively membrane aerators in the aeration system, and aerators of this type required replacement due to aging. After studying the international market, we decided in favor of using APKV tube air diffusers developed by Esmil and having the best technical specifications.

In 2018, the Esmil aeration system with APKV air diffusers was installed in the L4 aeration tank as the first step, and then in 2019 and early 2020, the same air diffusers were installed in the remaining 5 sections (L1-L3 and L5-L6).

Our experience with membrane diffusers after several years of operation can be described as follows:

  • Stretching of membrane plates;
  • Loss of elasticity of membrane plates;
  • The size of the air bubble increases due to the increase in the size of the perforation, and as a result, the oxygen dissolution efficiency decreases;
  • Physical damage, rupture of membranes;
  • Lack of oxygen at high loads;
  • Physical cleaning of the contaminated surfaces of the membranes does not fully restore their performance.

In order to maintain the required level of dissolved oxygen in the membrane aeration system, we had to empty the aeration tanks to inspect the membranes, clean them, and, if necessary, replace damaged membranes every two years. The main goal of replacing membrane aerators was to reduce excess maintenance costs of the aeration system.

The original APKV Esmil air diffusers were installed in the L4 aeration tank, which was 1/6th of the capacity (13,333 m3/day) of the total activated sludge flow rate. This was done for the purpose of comparison with the existing membrane system.

APKV Esmil air diffusers showed stable operation, the required intensity of aeration, the required parameters for oxygen saturation were achieved at a lower air pressure. SSOTE was 5 – 6.3%/m depending on the current air flow rate. The overall air consumption was reduced.

An additional positive effect was the significantly higher adaptability of the APKV Esmil system in terms of air supply regulation. New aeration system made it possible to more precisely and flexibly follow the changing oxygen demand, which makes it much easier to control the process and provides the necessary air supply, even during peak load periods.

As a result of the positive experience of operating the aeration system in the L4 aeration tank in 2019, a complete replacement of the aeration system was carried out in the same year and in 2020; APKV Esmil air diffusers were installed in the entire activated sludge system.

Experience in operating the aeration system using Esmil air diffusers:

  • Constant oxygen supply in the required amount during peak loads, DO 3-4 mg/l (including the last 8. cascade);
  • working pressure 535 mbar;
  • Reduction of pressure losses;
  • The air diffusers retain their shape, they are resistant to mechanical damage and corrosion;
  • The air diffusers do not get clogged.

Summarizing the above, it can be affirmed that the use of APKV Esmil air diffusers significantly reduces the need of service, and also meets the requirement for dissolved oxygen in activated sludge aeration tanks while reducing energy costs.


Case study: Brown’s Bay Packing Company (Campbell River, BC, Canada)

TYPE OF INDUSTRY – Fish processing
MODEL OF DAF-UNIT – FT-20Z with static mixer
START OF OPERATION – 2019 March

Issue

The customer was looking for the solution to reduce pollutants in wastewater from the fish processing plant, after the FBR advanced oxidation process. Moreover, they were looking for the compact and easy to operate system, with low operating costs.

Solution

Based on initial information and theoretical calculations, Esmil in cooperation with our representative in Canada Archer Separation Inc. offered DAF-unit FT-20Z.

Wastewater Sourceseawater with fish farm byproducts
Operating Time16-20 h/day, 3-4 days/week
Flow Rate20-40 m3/h
Feed TSS Concentration800-1200 ppm
Effluent TSS Concentration80-100 ppm

Case Study: Municipal Wastewater Treatment Plant (Bridge City, TX, USA)

MODEL OF DEHYDRATOR – MDQ-354(2) CL
START OF OPERATION – 2020 June

Issue

In the plant sludge drying beds for sludge dewatering were used. This method required lots of labor and constant maintenance. Due to this reason, the customer was looking for the efficient and minimal maintenance solution.

Solution

On-site pilot tests were carried out, using mobile dewatering unit MDQ-201, to find the best dewatering technology. According to the test results Esmil offered sludge dewatering complex based on Multidisc Screw Press Dehydrator MDQ-354(2) CL. The complex includes – influent sludge feed pump, polymer feeder, three screw conveyors and service platform.

Type of sludgeaerobically digested excess sludge
Operating timeup to 8 h/day, 3 days/week
Unit sludge capacityup to 9 (18*) m3/h
up to 320 (400*) kg DS/h
Inlet sludge DS content3.5 %
Cake DS contentapprox. 22-23 %
Polymer consumption14.6 l/tonDS
TSS concentration in filtrate200 ppm
DS capture rate99.4 %
*in case of adding two additional dewatering drums.

 

 

Case Study: Municipal Wastewater Treatment Plant (Webster, Texas, USA)

MODEL OF DEHYDRATOR – MDQ-354 C
START OF OPERATION – 2018 August

Issue

The customer had an interest in reducing sludge disposal costs in their municipal wastewater treatment plant by obtaining lower maintenance costs and lower energy consumption. The plant treats wastewater from nearby residential areas and numerous local restaurants and generates about 120 gallons of aerobically digested sludge from their digesters per minute.

Solution

On-site pilot tests were carried out, using mobile dewatering unit MDQ-201, to find the best dewatering technology. According to the test results Esmil offered sludge dewatering complex based on Multidisc Screw Press Dehydrator MDQ-354 C. The complex includes – macerator, polymer feeder and service platform.

Type of sludgeaerobically stabilized excess sludge
Operating time9-10 h/day, daily
Initial sludge capacity20 m3/h
310 kg DS/h
Inlet sludge DS content1.3-1.5 %
Cake DS content16-18 %
Polymer powder consumption8.8 g/kgDS
TSS concentration in filtrate70 ppm
DS capture rateup to 99.7 %

 

 

Case Study: Soapberry WWTP (Kingston, Jamaica)

MODEL OF DEHYDRATOR – MDQ-353 C
START OF OPERATION – 2020 February

Issue

Soapberry WWTP located near Kingston Harbour has been operated since 2004. Biological wastewater treatment process is based on wetland lagoons. The WWTP has not previously had any sludge processing equipment, therefore since the start-up of the plant lagoons have been gradually filled with dry solid particles. As a result, sludge accumulation had impact on biological process efficiency, because of the reduced effective volume of the lagoons. For this reason, customer was looking for the solution to clean the bottom of the lagoons and process the sludge.

Solution

The lagoons cover an area of nearly 6 km2. Bottom sludge from the lagoons is removed by remote controlled dredger supplied by Dragflow. For this reason, Esmil offered Mobile dewatering complex based on Multi-disc Screw Press Dehydrator MDQ-353 C. The complex includes mechanical screen, sludge tank, influent sludge feed pump, polymer solution preparation unit, polymer dosing pump, water tank, water pump and screw conveyors. All the equipment is mounted on the common platform. The complex can be fitted in a standard 40’ container or on a trailer, which allows an easy relocation.

Type of sludgebiologically digested lagoon sludge
Operating timeup to 23 h/day
Initial sludge capacity10-15 m3/h
Inlet sludge DS content2-3 %
Cake DS contentapprox. 23-26 %
Polymer powder consumption1-2 kg/tonDS
TSS concentration in filtrate100 ppm
DS capture ratemore than 99 %

Case Study: Municipal Wastewater Treatment Plant (Argentia, Newfoundland, Canada)

MODEL OF DEHYDRATOR – MDQ-102 C
START OF OPERATION – 2019 November

Issue

The customer was looking for a low-cost, yet reliable and easy to operate solution for sewage from a construction site of an offshore platform treatment.

Solution

Project was carried together with our partner MABAREX. Esmil offered Multi-disc Screw Press Dehydrator MDQ-102 C, which is the part of the containerized wastewater treatment plant.

Results

Type of sludgeexcess activated sludge from MBR
Operating time6-10 h/d
Unit sludge supply0.5-1 m3/h
Inlet sludge ds content0.5-1 %
Cake DS content15-17 %
Polymer consumption5 kg/ton DS
TSS concentration in filtrate20-100 ppm
DS capture ratemore than 98 %

Case Study: KB Bioenergy, inc. (Akron, OH, USA)

TYPE OF INDUSTRY – Renewable energy
MODEL OF DEHYDRATOR – MDQ-354 CL
START OF OPERATION – 2020 January

Issue

The customer was looking for a solution to replace one of the three existing centrifuges as well as to increase dry solid content, reduce energy consumption and improve operation.

Solution

On-site pilot tests were carried out, using mobile dewatering unit MDQ-201, to find the best dewatering technology. According to the test results Esmil offered sludge dewatering technology based on Multi-disc Screw Press Dehydrator MDQ-354 CL together with service platform.

Results

Type of sludgeanaerobically digested sludge
Operating time23 h/day, 6 days/week
Unit sludge supplyup to 78 gpm
up to 3,276 lbDS/h
Inlet sludge ds content8.4 %
Cake ds content26.5 %
Polymer consumption16.5 lb/ton DS
Tss concentration in filtrate350-500 ppm
Ds capture rateup to 99.4 %

Case Study: Guggisberg Cheese (Sugarcreek, OH, USA)

TYPE OF INDUSTRY – Dairy products
MODEL OF DEHYDRATOR – MDQ-353 C
START OF OPERATION – 2018 December

Issue

The customer had an interest in reducing sludge disposal costs in their industrial wastewater treatment plant by obtaining lower maintenance costs and lower energy consumption. The plant treats industrial wastewater from a nearby cheese factory and generates about 15,000 gallons of activated sludge from their MBR system per day.

Solution

On-site pilot tests were carried out, using mobile dewatering unit MDQ-201, to find the best dewatering technology. According to the test results Esmil offered sludge dewatering technology based on Multi-disc Screw
Press Dehydrator MDQ-353 C.

Results

Type of sludgeaerobically stabilized MBR sludge
Operating time8 h/day, up to 5 days/week
Unit sludge supplyup to 12 m3/h
up to 230 kgDS/h
Inlet sludge ds content2%
Cake DS contentapprox. 18-20%
Polymer consumption4.0 g/kg DS
TSS concentration in filtrate50 ppm
DS capture rate99.7%

Case Study: Modernization of the clarifiers (Awgustow, Poland)

PROJECT – Modernization of the secondary clarifier
CUSTOMER – Wodociągi i Kanalizacje Miejskie Sp. z o. o. w Augustowie
OBJECT – Wastewater Treatment Plant in Augustów
COMMISSIONING – October, 2018

Introduction

Wastewater Treatment Plant is located in the South part of the Augustów city. It is a mechanical-biological type of plant adapted for deep removal of the biogenic compounds. Water needs to pass several steps and once purifi ed, it is drained to the Netta river. The maximum capacity of the plant is 10 000 m3/day. In June 2018 PRODEKO-EŁK Sp.zo.o. (Esmil Industrial Group) has been chosen as a main devices and technology supplier to accomplish the task of secondary clarifi er modernization at the Wastewater Treatment Plant in Augustów.

Modernization purpose

The main goal of the modernization was to:

  • ensure the stable work of the secondary clarifier
  • increase the removal effi ciency of the fl oating parts and the sludge
  • decrease the operating costs

Initial stage

As part of the signed contract a radial sludge scraper ZGRwt-25 type and the penstock SGSM type have been supplied. The scope of work carried out included preparation of the documentation to fabricate the devices and necessary parts properly adapted to the dimensions of the clarifi er and the sewage disposal channel, as well as assembly and technological commissioning of the supplied devices.

Results and conclusions

The use of modern technological solutions in the design of devices ensures high work efficiency, energy efficiency and reliability. As a result of replacement of the existing sludge scraper at the Wastewater Treatment Plant in Augustów the following were achieved:

  • increase in the efficiency of floating parts and sludge removal due to the special design of the scraper elements;
  • high level of energy efficiency of the device due to the use of energy saving trolley drive with the gearbox embedded directly within the wheel;
  • lowered operating costs of the device related to maintenance and repair.